Abu Dhabi-based developer, Aldar Properties, have commenced handovers at Nareel Island, one of the most exclusive islands on the coast in Al Bateen.
Handovers have also commenced at Al Merief, Aldars plot development marketed to UAE Nationals, located in Khalifa City.
Construction currently continues to make strong progress across Aldars remaining developments. On Yas Island, at West Yas, construction is entering its final stages, with testing and commissioning work ongoing, in preparation for handover to customers.
Last week, Aldar awarded an AED1.3bn main contractor package for Waters Edge, which comprises 2,255 residential units, with exercise and recreation facilities, restaurants and cafes, retail space, and a waterfront promenade on Yas Islands eastern shores.
At Mayan, Aldars luxury golf and waterfront apartment development, substructure work is now complete with work on the superstructure well underway across the development. Similarly, at Yas Acres, building activity continues across all 652 villas and townhouses that have been launched to date.
On Reem Island, enabling work is making good progress at The Bridges, a six building, 1,272-home development on Reem Island, launched last year. Main works are expected to commence imminently. Meera is now almost fully enclosed and HVAC fixing is now complete across both towers.
In Al Ain, expansion and renovation work at Al Jimi Mall, Aldars flagship asset in Al Ain, is entering final stages. It is due to complete end of this year and set to add 33,000sqm of retail, leisure and F&B space, bringing total gross lease area (GLA) to 76,000sqm.