Limitless Downtown Jebel Ali master development in Dubai has reached more new milestones with Zone 2 infrastructure now complete and the first substation handed over to DEWA.
All underground utilities are now complete at Zone 2 of the 200ha mixed-use development, while 90% of work is finished at Zone 4, and 70% in Zone 3. Road construction is also complete at Zone 2, and underway at Zones 3 and 4. All infrastructure work at Downtown Jebel Ali is on track for completion in 2018. Meanwhile, a 132 kv substation was completed and handed over to DEWA in October.
Last week, Limitless announced an early repayment of AED412.4mn to banks and trade creditors. Ali Rashid Lootah, chairman of Limitless, said: Downtown Jebel Ali has seen major progress in the last few months, and these new milestones reinforce our commitment to the investors who share our vision for our flagship master community. 2017 has been a highly successful year for Limitless, and we look forward to even greater achievements in 2018 and
beyond.
Downtown Jebel Ali has more than 300 third party plots that will contain a mixture of apartment blocks, hotels, offices, and retail developments. Many are already operational or under construction.
Stretching 11km along Sheikh Zayed Road, the development is close to Jebel Ali Free Zone and within easy reach of Abu Dhabi, Dubai World Central Airport, the Expo 2020 site, and key attractions in Dubai.